MIL-DTL-20354D (AR)
4.4 Methods of inspection
4.4.1 Proving ground. These tests shall be conducted at a
Government proving ground. The sample cartridges shall be
fired with M67 propelling charges in a gun for which the
ammunition is standard and observation made for conformance
to all requirements (see 6.9 and 6.10).
4.4.1.1 Functioning. The sample cartridges shall be fired at
zone 7. If any of the sample cartridges used in any of the
tests fail to comply with the requirements as specified in
paragraph 3.5.2 the lots shall be rejected.
4.4.1.1.1 Production lot sampling. Beginning with the first
lot produced and continuing until three consecutive lots
have complied with the requirements as specified in
paragraph 3.5.1 herein, 80 cartridges shall be selected for
this test. If nine or more cartridges fail to function
satisfactorily or to provide effective illumination for at
least 55 seconds, the lot shall be rejected.
4.4.1.1.2 Production lot reduced sampling. After three
consecutive lots have met the criteria of 4.4.1.1.1, 34
cartridges shall be selected for this test. If five or more
fail to function satisfactorily or to provide effective
illumination for 55 seconds the lot shall be rejected. In
the event that three successive lots fail to meet the
requirements of 4.4.1.1.2, the sampling provisions of
4.4.1.1.1 shall again apply. When three consecutive lots
have again passed the requirements contained therein, the
provisions of 4.4.1.1.2 shall be reinstated.
4.4.1.2 Ballistic safety test. The sample cartridges shall
be fired with propelling charges adjusted to give 112
percent of the rated maximum pressure for the cartridge. In
addition, for the first three production lots from each
manufacturer (loading facility); a smear camera shall be
used to observe the projectile in flight in order to record
any possible malfunctioning.
4.4.1.2.1 Production lot sampling. Beginning with the first
lot produced and continuing until three consecutive lots
have complied with the requirements as specified in
paragraph 3.5.3 herein, 10 cartridges shall be selected for
this test. If any cartridge fails to comply with 3.5.2 the
lot shall be rejected.
4.4.1.2.2 Production lot reduced sampling. After three
consecutive lots have met the criteria of 4.4.1.3.1, three
cartridges shall be selected from each lot for this test. If
any cartridge fails to comply with the applicable
requirements the lot shall be rejected. In the event a lot
fails to meet the requirements of 4.4.1.3.2, the sampling
provisions of 4.4.1.3.1 shall again apply. When three